Our travelling exhibition, Sheila Hicks: 50 Years, has opened at its third and final venue at the Mint Museum of Craft + Design in Charlotte, NC. I wrote a post a while back about the challenges of traveling a show of this type. I was still trying to figure out how we were going to get this show to the places it was going. Now, as we near the end of the show’s run, I think I have managed to answer many of the questions I was asking at the end of that post.

Trucking the crates between venues required two tractor trailers: easily the largest show volume-wise the Addison has ever traveled. We were required to have a courier on one of the trucks, and I rode with the show from Philadelphia to Charlotte. Loading the trucks at the end of the show’s second venue at the ICA, Philadelphia was interesting, as their loading dock could not accommodate tractor trailers. We had no choice but to load in the sidewalk outside their front doors. Needless to say, getting some of the show’s massive crates down the sidewalk and up into the truck’s lift gate was indeed a challenge (see upper left). We left Philadelphia late afternoon and pulled into the Mint’s loading dock early the following morning. Sadly, I didn’t get much shut-eye despite the truck’s surprisingly ample sleeping quarters.

I’ve also travelled to each venue to oversee installation at the beginning and packing at the end. Installations were adventures, as each crew at each museum had to figure out the best way to display the objects in their unique settings. Just trying to figure out how to hang things from their ceilings required considerable planning, thought, and effort each time, while Sheila herself added her advice as to how things should look.

The Mint’s installation is certainly different from the other two. I’m always amazed how each museum interprets the same show for a unique experience. But it is beautiful, thanks to the Mint’s gorgeous new galleries, and, of course, the art itself. Sheila Hicks: 50 Years is up until January 29th when I return again to pack it up one last time and return the objects to their lenders. I encourage you to see it while you can!

Posted by:

James M. Sousa
Associate Registrar for Collections and Archives

Wednesday, October 5, 2011

The Collection Is Home, Safe and Sound

It has been a long six months watching the cranes outside lift huge structural beams and crates of glass atop our museum for our roof replacement project. But it did provide us with an opportunity to finish another project we had as a result of our renovations: the movement of the permanent collection. In earlier blog posts (click here and here), I wrote about the challenges of packing and moving our art collection off site in 2008 in preparation for handing our building over to contractors. Now, some three years later, the collection has finally returned.

Though a small fraction of the collection was brought back for our fall 2010 opening, the bulk of it remained off site. With our renovated storage areas ready to receive artwork (see right), we started transporting the collection back in early April. Each week, I’d drive down to FAE, Boston, where our artwork was being stored, oversee the truck being loaded, and follow the truck back to the museum. We would then offload at our new loading dock. Bringing the objects into the museum was far simpler than moving out, as everything had to be loaded on the trucks in 2008 from ground level using the truck’s lift gate. And, of course, we had left most everything packed from when we moved out, so repacking things for this trip was kept to a minimum.

It took twenty-six truck loads to bring our nearly 17,000 objects back to the museum (see left, one of our emptied storage areas at FAE). My colleagues and I then had to carefully unpack and inventory each and every object, properly store it, and update its location on the database. Depending on the size and type of the objects, some truckloads could bring back hundreds of objects, some only a couple of dozen. Thankfully, with the exception of two large outdoor sculptures that simply won’t fit through our doors, our new storage areas absorbed everything with ample room for growth.

Now, the new glass roof crowning our original Platt building is complete, artwork is being hung on the gallery walls again, and we’re set to reopen to the public Saturday, October 8th. For me, however, I can rest easy knowing that the Addison’s collection is finally home again, safe, sound, and dry, within the museum’s walls.


Posted by:

James M. Sousa
Associate Registrar for Collections and Archives

Thursday, July 21, 2011

Roof Update and a Look Ahead


Workmen cleaning the glass panels of the original roof, working above one of the horizontal beams that will support the new roof over the existing roof structure.

When the Addison reopens on October 8, the entire museum will have been renovated from top to bottom. The final phase of construction at the museum – the construction of a new glass roof to overlay the old – is progressing without a hitch, and will be completed in time for the Addison’s 80th birthday celebration this fall. Mark your calendars now for our opening reception on October 14, and black tie gala on November 3 (and watch our website and Facebook page for more information).

A 90-ton crane lifts one of the prefabricated metal components that will support the glass overlay, while workmen restore and re-point the chimney.

The completion of this new roof overlay is the exciting last step in preserving and restoring the Addison Gallery’s historic, classical revival building, designed by architect Charles A. Platt and opened in 1931. For the last 80 years, the museum’s glass roof has contributed to the essential character of the building’s exterior appearance and has enhanced the experience of viewing art by allowing UV-filtered natural light to fill the second floor galleries.

The glass panels are meticulously fitted, one by one, into the new metal roof structure.

The innovative approach to protecting and preserving the original roof by constructing a new, state-of-the-art glass overlay roof will allow the continuation of the viewing experience envisioned by the building’s architect. It is with pleasure that the school and the Addison have worked together to assure the retention of Charles Platt’s elegant architecture for generations to come.

The installation of the glass continues on the north side of the Addison roof as workmen prepare the lower face of the roof for its metal cladding.